Estimate the power of your transformer.

From the installed power, a simultaneity factor, the power factor and a reserve, this tool gives an order of magnitude for the power of the transformer. A load study must then confirm it.

Estimated apparent power—Next common rating above—

A first estimate. The transformer is chosen from a detailed load assessment.

Request a study

What the four inputs mean

The installed power is the sum of the power ratings of all the equipment on the site: machines, lighting, air conditioning, sockets. Not all of it runs at the same time, or at full load. The simultaneity factor reflects this: it brings the installed power down to the power the site actually draws at the same moment. It depends on the activity, and it is the hardest input to estimate without knowing how the site operates.

The power factor expresses the share of the power supplied that does useful work. Motors, in particular, lower it: the transformer then has to supply more for the same result, and it is this apparent power, expressed in kVA, that determines its size. Lastly, the reserve is the margin you keep for extensions: one more machine, an additional building, an activity that grows.

The inputs to enter

  • Installed power: the sum of the power ratings of the equipment
  • Simultaneity factor: the share actually drawn at the same moment
  • Power factor: the useful share of the power supplied
  • Reserve: the margin kept for extensions

Why the result remains a first estimate

The tool applies a single factor to the whole site. A load study, by contrast, works workshop by workshop and circuit by circuit: it takes account of motor starting, of equipment that runs in cycles, of loads that must stay supplied by a backup source and of any reactive power compensation. It may lead to a power different from the one given by an overall calculation, in either direction.

The result therefore serves to prepare a discussion, not to order a transformer. It gives an order of magnitude for a budget, a connection application or a first round of quotes. Before any commitment, the load assessment must be drawn up by a design office or by the contractor, from the actual list of equipment. In All Africa (IN2A) carries out this assessment as part of its transformer substation studies.

The equipment this guide is about

MV/LV substations · See the service

A model of principle: typical equipment, not the mock-up of a particular installation.

Your questions

01What is the risk with a wrongly sized transformer?

Too small, it runs overloaded, heats up, causes tripping and leaves no room for an extension. Too large, it costs more to buy and has higher losses, for power that is not used. The load study looks for the right level, reserve included.

02Where can I find the installed power of my site?

On the rating plates of the machines and in the data sheets provided by their suppliers, for a site at the planning stage. For an existing site, the switchboard diagrams and the electricity bills give useful pointers. A list of the equipment, even an incomplete one, is enough for a first estimate.

Related services

The In All Africa (IN2A) trades linked to this subject.

Let’s talk about your project

A power figure to have confirmed?

A work package to price, a substation to renovate, a home to equip: tell us what you need and we will get back to you.